The brief
Patuha-2 expands an established geothermal field on the Bandung plateau. The client required a matched set of two scrubbers and two atmospheric flash tanks, all rated for chloride-bearing two-phase steam at elevated temperature.
Schedule was driven by the turbine erection window. Vessels had to leave the Cikarang shop fully tested and documented in time for an over-dimensional convoy to the plateau.
Design considerations
Three failure modes governed the design: chloride pitting and stress-corrosion cracking of austenitic stainless, thermal cycling between hot operation and cold shutdown, and seismic loading per ASCE 7-16 for a Site Class D location.
Geothermal steam quality varies well-by-well. Internals were sized for the worst-case droplet load reported by the resource team, with a margin on demister area.
Materials & welding
SS316L was selected over 304L for chloride tolerance and over duplex for weldability at the wall thicknesses involved. Welding procedures were qualified on production-thickness coupons, with ferrite control and a maximum hardness target in the heat-affected zone.
Filler metals were lot-controlled. Each heat number was traced from mill certificate through to the final hydrotest report.
Fabrication highlights
Shell courses were rolled on the 80 mm plate roll and fit-up was completed on the rotator beds. Longitudinal seams were GTAW root with SAW fill and cap; circumferential seams followed the same procedure stack.
Phased-array ultrasonic testing of the longitudinal seams ran in parallel with fit-up of the next course to compress the critical path.
Testing & documentation
The third-party inspector witnessed weld-procedure qualification, PWHT cycles, NDE on production welds, and the hydrotest at 1.43 × design pressure. A helium leak test followed for the final box-up.
The Manufacturer's Data Report was issued in the client's template with full traceability — heat numbers, NDE film, PWHT charts and hydrotest curves cross-referenced to the weld map.
Delivery
Each vessel shipped as a single piece on a low-bed trailer under over-dimensional permit. Route survey, escort and bridge checks were coordinated with the EPC logistics team. Site reception, off-loading and setting on the foundation were witnessed by SKM field staff.
“The vessels arrived on schedule with a clean dossier. That is rare on a geothermal package of this size.”
Delivered.
All four vessels were delivered within the contracted window with zero NDE rejects on first submission. The MDR was accepted by the third-party inspector without revision.
The same procedure stack is now the reference for follow-on geothermal scrubber inquiries.